Saturday, February 27, 2010

Schedule

Project start date: Feb 22 
  • Week 1-5  Demo basement & underpinning; install in-floor heat; rough in drains and ejector box.
  • Week 6-9  Wait for concrete to dry; install windows; replace exterior & interior doors; drop boiler & hook up floor heat; electrical rough-in; ceiling (up to 2 weeks where no work happening)
  • Week 10  Polish Concrete (2 days)
  • Week 10-11  Frame & insulate walls
  • Week 11-12  Install stairs & railing; drywall
  • Week 12-13  Tile shower; install doors & trim
  • Week 13-14  Paint; install fixtures; finish electrical
  • Week 15  Detailing 
Project completion: June 4