- Week 1-5 Demo basement & underpinning; install in-floor heat; rough in drains and ejector box.
- Week 6-9 Wait for concrete to dry; install windows; replace exterior & interior doors; drop boiler & hook up floor heat; electrical rough-in; ceiling (up to 2 weeks where no work happening)
- Week 10 Polish Concrete (2 days)
- Week 10-11 Frame & insulate walls
- Week 11-12 Install stairs & railing; drywall
- Week 12-13 Tile shower; install doors & trim
- Week 13-14 Paint; install fixtures; finish electrical
- Week 15 Detailing
Saturday, February 27, 2010
Schedule
Project start date: Feb 22